Downtown Roswell Parking Deck Guide for Canton Street Visits

Right now the cheapest place to park for a Canton Street dinner is the new city deck at 1056 Alpharetta Street. Parking there costs nothing, and it costs nothing only because Green Street is still closed. The City of Roswell set the free period to last as long as the Green Street construction does. It didn't pick a calendar date. The city's original estimate had that construction finishing around now.

Free deck parking has no announced end date. When the street reopens, the free parking ends with it. The downtown parking pilot that sets every rate on Canton Street runs through December 31, 2026. For anyone who heads downtown on weekday evenings, the next ten weeks may be the last stretch when the deck and the curb charge such different prices.

The free deck started as a construction fix

Free parking wasn't the original plan. On March 9, 2026, Roswell City Council voted 4–2 to approve a parking pilot program. It covered the Green Street deck, which was still being built, and city-managed on-street parking through the end of 2026. The deck's role in that pilot framework was free parking on weekdays from 8 a.m. to 4 p.m., with paid parking on weekday evenings and weekends.

Soon after that vote, the city and its contractor assessed the Green Street Activation Plan. They found that Green Street would have to close fully to through-traffic between Cherry Way and Alpharetta Street (Highway 9). The full closure shortened the job from roughly 12 months to roughly six. The gravel lot at 1056 Green Street, which the pilot had set aside as downtown employee parking, became a construction staging area. Losing that lot is the reason the city gives for making the deck free during construction. "We understand how important convenient parking is for our downtown businesses, employees, and visitors," Mayor Mary Robichaux said in the city's announcement on Roswell Connections.

The deck opened on Monday, May 4, 2026, and Green Street work began the same day. The city called the closure "approximately six months" and projected that the improved street would open in fall 2026.

What an evening on Canton Street costs at the curb

On-street parking moved the other way. Starting August 1, 2026, the city changed downtown curb rates. The first two hours are free, but only for sessions that start between 8 a.m. and 3 p.m. After that, parking costs $3 an hour, up from $2, with a $24 daily maximum. A session that starts after 3 p.m. pays $3 an hour from the first minute.

These rates apply on Canton Street between Magnolia Street and Norcross Street, on Elizabeth Way between Canton Street and Alpharetta Highway, on East Alley between Canton Street and Norcross Street, and in the East Alley Parking Lot.

Here's how those rules work out for a few typical trips, compared with the deck as it's priced today:

Trip Downtown curb parking City deck during construction
Coffee run, 30 minutes Free in either of the two 30-minute spaces on Elizabeth Way Free
Lunch at noon, two hours Free Free
Shopping from 1 p.m. to 4 p.m. $3 for the third hour Free
Dinner at 6:30 p.m., two hours $6 Free
Saturday evening, four hours from 5 p.m. $12 Free

The curb figures come from the city's posted rate structure as of August 1, 2026. The deck column holds only while Green Street construction lasts.

The table shows that midday visits cost about the same in either spot. The difference shows up after 3 p.m., which is when Canton Street does most of its dinner business.

You still have to start a session at the curb, even during the free window. The city lets drivers pay by QR code, by text, or at two kiosks, so no app download is required. The city has named 12 Oaks Parking, LLC as the operations manager for downtown parking.

Getting into the deck while Green Street is closed

Most people approach downtown from Green Street, so the deck is easy to miss. While construction continues, the way in is from Alpharetta Street onto Kevin Cash Memorial Drive, which has one entrance and two exits. The connector road is named for Roswell Firefighter Kevin Cash, who died in the line of duty on January 21, 2020.

It's a big building by Roswell's standards. With 394 spaces, the deck is the largest facility the city has built since City Hall went up in the early 1990s. It was paid for with $20 million from the $179.6 million bond package Roswell voters approved in November 2022. The brick façade wraps all four sides, and tower-like stairwells at the corners make it easy to spot from Alpharetta Street. In late July, the city said early usage data was strong.

The city also says pedestrians can still reach downtown businesses during construction, and it asks visitors to follow the posted pedestrian signs.

What the finished Green Street adds

When the closure ends, Green Street will be a different street. The Activation Plan makes it one-way southbound and adds a brick-paved multi-use trail, underground utilities, new lighting, and landscaping. The section from Woodstock Road to Cherry Way has stayed open to southbound traffic throughout.

The piece that matters most for walking to Canton Street is a trail connection from Plum Tree Street to Canton Street. The city calls it "eventual" and hasn't given it a date.

Another project is lined up behind this one. On August 10, council voted to apply for up to $3 million in loans and $1.5 million in grants from the Georgia Transportation Infrastructure Bank for a Green Street Mobility Project. The vote first split 2–2, Mayor Robichaux broke the tie in favor, and the final count was 3–2. Councilmember Sarah Beeson recused herself, citing personal property next to the area. Appen Media reported that the project would improve pedestrian connections along Green Street from the parking deck to Woodstock Park. The deck is meant to anchor a walking network, and most of that network hasn't been built yet.

Four decisions the city hasn't announced

Recaps from council's September 28 and October 13 meetings show no new parking action. These decisions are still pending:

  1. The day the deck starts charging. Free parking is tied to the construction period, and the city hasn't announced a reopening date for Green Street.
  2. What the deck will charge. The only schedule the city has published is the March pilot framework: free weekday daytime parking, with evenings and weekends paid. That framework left the rates to the City Administrator, and it was written before the construction change.
  3. What happens after December 31. The pilot that sets the August curb rates is designed to collect data on demand and usage, and that data is supposed to shape longer-term parking policy.
  4. Parking at Hillrose and City Hall. In March, council postponed decisions on parking at City Hall and at the coming Hillrose development across the street until staff gathered more data.

The holiday season falls inside that uncertainty. The city's Annual Lighting of the Christmas Tree is Friday, December 4, 2026, from 6 to 8 p.m. at Heart of Roswell Park, 925 Canton St. It's free and open to the public. The event starts after 3 p.m., so curb parking will cost $3 an hour from arrival. The deck's price that night depends on whether Green Street has reopened by then.

Where the walk from the deck leads

Several downtown businesses have reached milestones since the deck opened. In its summer 2026 ribbon-cutting roundup, Roswell Inc listed these:

  • Hugo's Oyster Bar finished an expansion with a new enclosed patio and a bigger dining room.
  • Bellini Osteria Toscana held its grand reopening after a fire earlier in the year.
  • West + Peak, a custom candle studio, moved and opened Roswell Supply Co. next to it, offering Sip + Pour workshops and local apparel.
  • Social House opened in Historic Roswell as a nonprofit event venue in partnership with Home Church Roswell, with rental proceeds going to The Drake House.
  • V's Coffee Collab, founded by a local musician, opened with a portion of each purchase going to support independent local artists.
  • Spice of Thai marked new ownership with a redesigned interior, and Jeremiah's Italian Ice opened as owner Nahalia Thomas's first location.

More is on the way. Rough Draft Atlanta reported that Hal's "The Steakhouse" plans to open downtown next spring, a few doors from Little Alley Steak at Canton Street and Elizabeth Way, with a rooftop patio and valet parking. The free third-Thursday Alive in Roswell series wrapped its 2026 season on October 15, so most downtown visits between now and the tree lighting will be ordinary dinners, shopping trips, and errands.

As of this week, the deck at 1056 Alpharetta Street is still free. Reach it from Alpharetta Street by turning onto Kevin Cash Memorial Drive.

If you own a home near Green Street or anywhere within walking distance of Canton Street, a finished street, a new trail, and a 394-space deck all affect how buyers will see your location. Aretha Langley follows these downtown changes closely and can show you how they factor into your home's current value. Get your free home valuation.

Work With Aretha

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.

Follow Me on Instagram